Nieuws - 02 March, 2018

Steel structure parking garage Eindhoven (NL) nearly mounted


The steel structure of the new parking garage at the Brain Port Industries Campus in Eindhoven (NL) is nearly finished. About three quarters of the 450 tonnes of steel has now been mounted.

Short construction process

Voortman Steel Construction also supplies and mounts the TT floors, stairs and railings, fencing and cladding. The parties concerned coordinated the integral project approach at an early stage, thus realizing an efficient and quick construction process. Together with its principal EZ Park and a team of chain partners Voortman is continuously optimizing the construction process of parking garages, in order to build these even more cost efficiently.

Characteristics parking garage

Dimension                                           : 64 x 83 metres (l x w)
Number of parking spaces              : 972
Number of layers                               : 5 (including ground floor)
Cycle shed                                           : 194 bicycles
Construction time steel structure  : 13 weeks

About Brainport Industries Campus