Nieuws - 31 August, 2017

Car park at Wageningen University campus


Voortman Steel Construction will soon start the realisation of another parking garage, once again assigned by EZ Park. This time the location is the Wageningen University & Research Campus.

Start of the activities

The new parking garage provides space for 422 cars and the car park outside for another 32 cars. The façade of the parking garage will be executed in a combination of wood and planting. The assembly team of Voortman Steel Construction will start its activities by mid-October, which they will finish after approximately seven weeks. The completion of the parking garage is scheduled for the beginning of 2018.

Benefits of building together

Chain partners Voortman Steel Construction and EZ Park have already realised several car parks together. Last May, they completed the extension of the car park of Vanderlande which they built together in 2014. Important benefits of the cooperation are a fast development process and a short construction time. The complete supply of Voortman also contributes to this. Next to the steel structure, Voortman supplies and assembles the concrete floors, staircases and fencing.

Key figures

  • Number of parking spaces: 422 inside and 32 outside
  • Number of parking decks: 3 (ground level + 2)
  • Construction time steel structure: 7 weeks